01 / The product brief
What must the factory receive before it quotes?
A factory cannot quote reliably against a photograph and a desired retail price. Give each shortlisted manufacturer the same controlled brief: materials or ingredients, size, performance, finish, pack dimensions, required shelf life where relevant, target order quantity, tolerances, test method, delivery location and the version number of every file. Specify which inputs are fixed and which may be proposed as alternatives. A quote can then be compared against a common product, rather than against seven different interpretations of it.
Separate the prototype from the production standard. A hand-finished sample may prove appearance but not the line's ability to repeat it. Ask for a pre-production sample made with the intended process, materials and packaging. Sign and date the approved version, retain a counter-sample, and put any later change through a written revision. That paper trail protects both parties when a batch looks unlike the sample the founder remembers.
- One specification version for every bidder
- Approved production sample and retained counter-sample
- Named owner for artwork, formula, moulds and test data
02 / The category
Which approvals must be checked before production?
Start with the exact product and intended claims. Food, cosmetics, electrical goods and other regulated categories do not share one approval path. For food, use FoSCoS to determine the activity and relevant FSSAI registration or licence. For a product that may fall under a BIS Quality Control Order, check the current compulsory-certification list and the manufacturer's relevant licence. Do not accept a certificate for another factory or another product as proof that this batch is covered.
Packaging compliance is part of the product specification, not a task for the final week. Retail pre-packaged goods can require declarations such as name and address of manufacturer or packer, commodity name, net quantity, manufacture date, MRP and consumer-care details. Category-specific law and later amendments can add or alter duties. Have a competent reviewer approve the exact sale pack and online listing copy before artwork is frozen.
| Question | Evidence to request | Decision |
|---|---|---|
| Is the product regulated? | Current rule or order for the exact category | Do not produce before scope is clear |
| Does the site hold the right approval? | Current licence and factory address | Match the production site |
| Is the pack ready? | Approved proof and applicable declaration checklist | Release artwork only after review |
03 / The quality agreement
How will a failed batch be recognised and handled?
Write acceptance criteria before goods exist. For physical products, distinguish critical failures that make an item unsafe or unusable, major failures that undermine the promise, and minor cosmetic variation. Decide which dimensions, weights, ingredients, functions or labels will be tested; who samples; which method and laboratory apply; and what percentage or count triggers a hold. Without a pre-agreed method, a founder and factory can disagree honestly about whether the same batch passed.
Then write the remedy. State who pays for retesting, sorting, rework, replacement, return freight and disposal when a batch fails. Identify how a suspected defect will be traced to a production date and input lot. The agreement should include a stop-ship path for safety or labelling problems, and a recall decision owner if the product has already reached customers. These clauses are more useful than a broad promise to provide good quality.
- Inspection point and sample size
- Critical, major and minor defect definitions
- Hold, rework, replacement and return terms
- Batch and input traceability
04 / The order
What must the purchase order settle?
The purchase order should resolve minimum order quantity, unit price, taxes, payment milestones, lead time, delivery terms, approved subcontracting, spare material, overrun allowance and ownership of rejects. Ask what the quoted price excludes. A cheaper factory-gate number can become the expensive offer after tooling, printing, freight, storage, damage and rework are counted. Compare cash tied up before sale, not just gross margin on a spreadsheet.
Schedule a small first production run whenever the process permits. Confirm who signs off the pre-production sample, who can authorise a specification change, and which evidence releases the final payment. Leave room for one learning cycle: actual customer complaints, damage rates and repeat orders can justify a revision. The goal is not to pretend the first version is perfect. It is to make every change deliberate and traceable.